How long does office furniture installation take?
+
On-site installation of office furniture typically takes 1–5 working days depending on seat count: 1–2 days for 10–25 seats, 2–3 days for 50 seats, 3–5 days for a full 100-seat corporate floor. This is the installation phase only — total project timeline including manufacturing and delivery is usually 3–4 weeks for a 100-seat office.
What is a typical office furniture project timeline in India?
+
For a 100-seat corporate office in India, the typical end-to-end timeline is 3–4 weeks from purchase order: 10–14 days for in-house manufacturing, 1–3 days for delivery, 3–5 days for on-site installation, and 1 day for handover. Ezeefit manufactures at its Bhiwandi facility and handles the full execution under one roof, which compresses the timeline compared to multi-vendor projects.
Can a 100-seat office be furnished in 2 weeks?
+
A 100-seat office can be furnished in roughly 2.5–3 weeks if the CAD layout, BOM and finishes are signed off on day zero and the order is placed during a non-peak production slot. The constraints are manufacturing capacity (10–14 days for 100 workstations) and installation crew availability (3–5 days on-site). A pre-confirmed slot at the factory is the single biggest accelerator.
What factors slow down office furniture installation?
+
The most common delays are: (1) layout / specification changes after PO, (2) site-readiness issues — flooring, electrical, HVAC not complete, (3) restricted goods-lift or after-hours-only access at the building, (4) custom finishes requiring imported materials, (5) cabin/partition glass that needs longer toughening lead times. Ezeefit's design team flags all of these during the pre-PO site survey to keep the timeline on track.
Does Ezeefit handle phased installation for occupied offices?
+
Yes. For offices that remain occupied during fit-out, Ezeefit phases the installation by zone or after business hours (typically 7 pm to 7 am, including weekends). This is common for BPO / IT floors that cannot shut operations. A typical 250-seat phased installation runs 5–8 days of after-hours work with no daytime disruption.
Is delivery included in office furniture installation?
+
Yes. Every Ezeefit project includes manufacturing, delivery and on-site installation under a single project quote. No separate transport, labour or assembly contractor is required. Materials are dispatched from the Bhiwandi facility directly to the client site with the installation crew co-ordinated for the same window.
What does the installation team do on site?
+
Ezeefit's installation crew handles: workstation assembly and levelling, partition and cabin erection, cable and power routing within the desk spine, storage and pedestal placement, meeting-pod positioning and connection, glass-door alignment, chair unboxing and adjustment, and final clean-up. A site supervisor signs off snag-list rectifications before handover.
Can installation begin before the entire site is ready?
+
Partial installation can begin once the flooring is finished and the area is electrically and HVAC-ready in the first zone, even if other zones are still under civil work. This is a common time-saving technique for large floors — the installation crew works zone-by-zone behind the civil team, compressing the overall handover by 5–10 days.